BlackGold

BlackGold

Oil Sands Project

The BlackGold Oil Sands Project is located approximately 10 km southeast of Conklin, Alberta. Acquired from Korea National Oil Corporation (KNOC) in 2010, construction and development of the project began later that year.  At the end of 2016, Harvest’s BlackGold oil sands property had Proved Undeveloped bitumen reserves of 96.0 MMbbl and Probable Undeveloped bitumen reserves of 163.2 MMbbl and are located in close proximity to a number of major oil sands developments in the Conklin Region of Northeastern Alberta.

Phase 1 of the project (the Initial Project) was designed to produce 10,000 bpd. Approval for BlackGold’s first phase has already been granted by the Energy Resources Conservation Board (ERCB) and Alberta Environment (AENV). BlackGold’s second phase (the Expansion Project), which was approved in December 2013, is targeted to increase production to 30,000 bpd. The BlackGold Project is expected to produce over a period of approximately 25 years. BlackGold Reserves will be recovered by using SAGD methodology.

BlackGold will utilize Steam Assisted Gravity Drainage (SAGD), a proven in situ production technology that uses horizontal drilling and thermal stimulation to maximize energy and production efficiency and minimize surface land disturbance.

Harvest Operations Corp. maintains 100% working interest and operatorship of the BlackGold project.

Background
SAGD 101
Site

Background

BlackGold Oilsands Project

The BlackGold oil sands project is located in the bitumen-rich southern Athabasca oil sands region of Alberta. Harvest has a 100% working interest in 15 sections of oil sands leases, located in Township 76, Range 7 West of the 4th Meridian. This area is ideally suited to in situ SAGD development

 

The project began in March of 2008 with the initial application for approval to construct, operate and reclaim the oil sands to produce at a design capacity of 10,000 barrels per day of bitumen using steam assisted gravity drainage (SAGD) technology. The initial project was approved by regulators in March 2010.

The construction of the production facility is ongoing and the first 15 SAGD well pairs from two well pads were successfully drilled in October 2012.

The Project was completed and started in 2018 with ramp up to full nameplate capacity in 2019.

Phase 2 of the project includes plans to expand production to a design capacity 20,000 additional barrels per day of bitumen to make combined production of 30,000 barrels per day.

Up to 200 SAGD well pairs from as many as 30 well pads will be drilled to maintain the production capacity of 30,000 barrel per day from the McMurray and Wabiskaw formations over a period of approximately 30 years..

SAGD 101

Steam Assisted Gravity Drainage (SAGD) Overview

SAGD technology is a well-recognized and proven commercial in situ thermal recovery process, which we are applying at BlackGold for bitumen extraction from the McMurray and Wabiskaw formations in the Athabasca oil sands area.

SAGD involves drilling of two parallel wells for each well pair. One well in each pair is used as a steam injection well and is placed ~5m above the bottom wellbore, that is used as Bitumen and Produced Water Emulsion Production Well.

In the BlackGold project a pair of 650-~850m horizontal wells drilled in parallel within the McMurray and Wabiskaw resevoirs. These resevoirs are approximately 350-400 metres underneath the surface. The well pair wells, injector and producer, have a vertical separation of approximately 5 metres. The production wells will be placed approximately 1 metre above the base of the bitumen column. As steam is injected into the resevoir and the surrounding bitumen reserves are heated up, the bitumen becomes less viscous and flows into the producing well. Down hold pumps then transfer the bitumen to the surface. The pressure chamber can be controlled by means of steam injection and Emulsion Production rate adjustments.

 

The project began in March of 2008 with the initial application for approval to construct, operate and reclaim the oil sands to produce at a design capacity of 10,000 barrels per day of bitumen using steam assisted gravity drainage (SAGD) technology. The initial project was approved by regulators in March 2010.

The construction of the production facility is ongoing and the first 15 SAGD well pairs from two well pads were successfully drilled in October 2012.

The Project was completed and started in 2018 with ramp up to full nameplate capacity in 2019.

Phase 2 of the project includes plans to expand production to a design capacity 20,000 additional barrels per day of bitumen to make combined production of 30,000 barrels per day.

Up to 200 SAGD well pairs from as many as 30 well pads will be drilled to maintain the production capacity of 30,000 barrel per day from the McMurray and Wabiskaw formations over a period of approximately 30 years..

Site

Both Phase 1 and Phase 2 of the project will operate as one facility.


Inquiries related to BlackGold can be directed to:blackgold@harvestenergy.ca